High-voltage motor disassembly and maintenance techniques
2025-04-28
Author:
1. When disassembling the motor from the equipment, mark the parts with special assembly requirements and save the disassembled parts.
2. When removing the rotor, be careful not to scratch the stator winding insulation. Observe whether the motor bearings are worn, and whether the lubricating oil is deteriorated or dry. Hold the outer ring of the bearing and shake it back and forth to see if it is loose. Rotate the outer ring of the bearing to observe whether there is any jamming or abnormal noise. If normal, it can be cleaned with kerosene or diesel oil without disassembly. If there is a problem with the bearing, use a puller to remove the bearing.
3. If the rotor shaft and bearing are too tight or rusted, heating can be used to solve the problem. Wrap the rotor shaft with asbestos rope, and use a blowtorch or oxy-acetylene flame to quickly and evenly heat the bearing to 250℃, and use a puller to pull it out while it is hot. Or pad the bottom of the bad bearing with a wooden board, and use an iron hammer to break the outer ring of the bearing and remove the outer ring. Use a hand grinder blade to cut a notch in the inner ring of the bearing (do not cut through it to avoid damaging the rotor shaft), then tap the inner ring to crack the notch, and then remove the inner ring.
4. When replacing the bearing, it is best to preheat the bearing. When the temperature reaches about 100℃, put the bearing on the rotor shaft while it is hot. For larger bearings, place the bearing in a metal container with lubricating oil, place two chopsticks under the bearing, and heat it on an electric stove until the oil boils. After a few minutes, take out the bearing and put it on the rotor shaft while it is hot, and use a copper rod to support the inner ring of the bearing. Tap evenly on both sides to make it in place. Note that when installing the bearing, the bearing with the model should face outwards, which is convenient for checking and replacing in the future.
5. Add lubricating grease according to 1/2 of the inner space capacity of the bearing. For high-speed bearings, add a little less, and do not add too much lubricating grease. Excessive lubricating grease will cause the high-pressure motor to overheat, the thinned lubricating grease will flow out along the oil seal cover, be swept onto the stator winding by the rotor internal fan blades, reduce the insulation performance of the winding, cause breakdown and short circuit, and burn out the motor winding.
6. If iron filings and sand grains are mixed into the lubricating grease, it will cause the bearing to wear faster and cause premature bearing damage.
7. Commonly used lubricating greases include calcium-based grease and sodium-based grease. Calcium-based grease has better water resistance but poor heat resistance, suitable for working conditions below 70℃. Sodium-based grease has poor water resistance but good heat resistance, suitable for working conditions below 120℃. Electricians should choose lubricating grease reasonably according to the working environment and working conditions of the motor.
8. When assembling the motor, install the rear end cover first. Place the shorter end of the rotor shaft vertically upwards, put on the rear end cover and place it flat, use a wooden hammer to gently tap the end cover left and right, and simultaneously rotate the end cover slowly on the shaft, so that the bearing is evenly stressed during the process of entering the shaft sleeve, and the bearing seat is not damaged. After it is in place, if the rear end cover has an oil seal cover, tighten the oil seal cover screws.
9. Carefully insert the rotor into the stator, close the rear end cover, and tighten the rear end cover screws in an alternating diagonal order. Then, install the front end cover in the same way as the rear end cover and tighten the screws. If the front end cover has an inner oil seal cover, and it is inconvenient to install the fixing screws because the end cover holes do not align, the following method can be used: Find a piece of iron wire with a diameter of about 2mm, bend a right angle at 30mm, insert the iron wire into the inner oil seal cover screw hole, and when installing the front end cover, insert the iron wire into the front end cover oil seal screw hole. Install the front end cover according to the above method, then tighten the iron wire to align the oil seal cover holes, tighten the last screw after tightening the two fixing screws, and then forcefully pull out the iron wire in the hole.
10. Finally, rotate the rotor to see if it rotates flexibly, whether there is any looseness, whether there is any noise in the bearing, and whether the screws are firmly installed, then install the fan blades and fan cover. Use a megohmmeter to measure the insulation resistance of the winding, connect the power supply to test the machine, and use a clamp meter to measure whether the three-phase current is balanced.
Previous Page:
Next Page:
Consult Now
If you are interested in our products, please leave your email, and we will contact you as soon as possible. Thank you!
Related Blog
Contact Us
Shenyang Electric Machinery Manufacturing Co., Ltd.
Address: No.24, Kaifa No.24 Road, Shenyang Economic and Technological Development Zone, Liaoning Province, China
Telephone:+86 24 8600 9926
Email:sydj_xs@163.com